PROJECT EXPERIENCE


Gama Intisamudera has executed a number of projects with local entities in Indonesia such as PT Rekayasa Industri , PT Pertamina Persero, PT Inti Karya Persada Teknik and PT. Pelindo. We mainly handle heavy lift transportation, skidding and jacking, ship-to-ship operation as well as gantry relocation.
During our project operation, we use diverse equipment to ensure safety, high quality service, and customer satisfaction. We are supported by an extensive range of equipment ranging from prime mover & head truck, to hydraulic jack, to multi axle. Our latest project is domestic services handling for Jambaran Tiung Biru Project and Refinery Development Master Plan RU-V Balikpapan Project.

October 2016
PETROKIMIA GRESIK AMUR II PROJECT
H2S Absorber 650 Ton
Equipment :
  • Goldhofer PST - SL 6 & THP - SL 14
Transport Route :
Petrokimia Gresik Jetty to Amur II Site
October 2016
PETROKIMIA GRESIK AMUR II PROJECT
Delivery Steam Drum 100 Ton
Equipment :
  • Prime Mover MAN TGS 40.440
  • Goldhofer THP/SL 20 Axle
Transport Route :
Roll-Off From Barge to AMUR II Site
April 2014
Lombok CFSPP FTP-2 2 X 50 MW
Rafako Shipment
Equipment :
  • Prime Mover MAN TGS 40.440
  • Goldhofer THP - SL 8 Axle
Transport Route :
Site Jetty to Site
April 2014
Pelindo I
2 Unit HPC 450 Ton Relocation
Equipment :
  • Ballasting Pump Set
  • Rampway
Transport Route :
Jamrud Port to EPC V Bojonegoro Site
April 2014
BMC Logistics - Pelindo III
1 Unit HMC Relocation
Equipment :
  • Ballasting Pump Set
  • Rampway
Transport Route :
Berlian Port Terminal to Jamrud Terminal Port
April 2014
PAITON UNIT 3 - POMI
Delivery 1 Unit Transformer 550KVA 350 Ton
Equipment :
  • Barge 230 Feet
  • PST - SL 6 Axle & THP - SL 18 Axle
  • Jacking and Skidding System
Transport Route :
Jetty Siemens - Foundation
April 2014
Lombok CFSPP FTP-2 2 X 50 MW
2 X 100KVA GSUT Shipment
Equipment :
  • Prime Mover MAN TGS 40.440
  • Goldhofer THP - SL 8 Axle
Transport Route :
Site Jetty to Site
December 2018
PLTMG SORONG 1 X 50 MW PROJECT
Ship to Ship Operation
Equipment :
  • LCT Ayu 168 (1500 DWT)
Transport Route :
Sorong Port
December 2018
PLTMG SORONG 1 X 50 MW PROJECT
Delivery 3 Units Wartsila Engine 140 Ton Each
Equipment :
  • Prime Mover MAN 40.440
  • Goldhofer THP/SL 10 Axle
Transport Route :
Petrogas Jetty to Site